Structural Steel Bid / No-Bid Checklist

A practical first-pass screen for fabricators and erectors. Use it before investing hours in takeoff, vendor pricing, and subcontractor outreach.

1. Confirm the opportunity is live

  • Open the issuing agency or contractor's original posting; never rely on an email date alone.
  • Record the exact bid deadline, time zone, delivery method, pre-bid meeting, and question deadline.
  • Download the latest addenda and confirm whether acknowledging each addendum is mandatory.
  • Check whether this is a prime bid, subcontractor bid, budget price, prequalification, or request for qualifications.

2. Locate the steel scope

Start with the structural general notes, framing plans, schedules, and these common specification sections. The contract may divide responsibility differently, so verify the drawings, specifications, and bid form together.

ScopeCommon locationQuestions to answer
Structural framing05 12 00; S-series drawingsMember grades, connections, delegated design, camber, testing
Joists and deck05 21 00 / 05 31 00; roof and floor plansJoist designation, bridging, deck type/gage, sidelaps, openings
Miscellaneous metals05 50 00; architectural and structural detailsStairs, rails, ladders, embeds, lintels, bollards, supports
Coatings05 05 13, 09 91 00, finish schedulesShop prime, galvanizing, intumescent coating, touch-up, exposed steel
ErectionDivision 01, 05, logistics drawingsCrane access, phasing, temporary bracing, field welding, surveys

3. Screen commercial and schedule risk

  • Does the project fit your geographic radius, shop capacity, certification, bonding, and insurance?
  • Can mills and vendors support the required material grades, domestic-content rules, finishes, and delivery dates?
  • Are liquidated damages, retainage, payment terms, bid security, performance bonds, or unusual indemnity terms disclosed?
  • Is there enough time for takeoff, connection assumptions, subcontractor quotes, review, and a clean proposal?
  • Does the apparent project value justify the estimating effort and opportunity cost?

4. Use a simple bid / no-bid score

Score each item from 0 (poor) to 2 (strong). A total is a decision aid, not a substitute for judgment.

Factor012
Scope fitOutside capabilitiesManageable stretchCore work
Capacity and scheduleConflictTightGood fit
DocumentsIncompleteSome gapsComplete enough
Customer / competitionUnknown or poor fitNeutralKnown opportunity
Commercial termsUnacceptableNeeds exceptionsAcceptable
Margin potentialLowUnclearAttractive

Suggested interpretation: 10–12 merits immediate pursuit; 7–9 needs a manager review; 0–6 is usually a no-bid unless there is a strategic reason.

5. Before submitting

  • Reconcile takeoff, inclusions, exclusions, alternates, allowances, freight, tax, escalation, and erection assumptions.
  • Confirm the proposal uses the required form and includes signatures, acknowledgements, bonds, licenses, and certifications.
  • State what is included clearly enough that the customer can compare bids without guessing.
  • Perform an independent final review of quantities, extensions, schedule, and submission instructions.

This checklist is general estimating guidance. The solicitation and contract documents control.